Kenya sinks Sh1.86bn more into foreign mission upgrades

Nairobi spent an additional Sh1.86 billion on the upgrade of property hosting its foreign missions in the year to June 2026, in a race to complete half-finished embassy repair projects around the world that have trapped billions of shillings.

The latest expenditure brings cumulative spending on the projects to Sh5.5 billion against an estimated Sh9.34 billion total cost, leaving Sh3.84 billion in outstanding bills.

Spending data from the State Department for Foreign Affairs shows that the amount spent by the government reflects continued investment in maintaining, upgrading and expanding Kenya’s overseas property portfolio.

However, several projects remain far from completion despite years of spending, raising questions about implementation timelines and the cost of maintaining government-owned properties in foreign capitals.

The largest allocations in the year under review went to New York and London, which together absorbed Sh1.1 billion, accounting for nearly 59.2 percent of the annual expenditure.

The New York redevelopment project received Sh550 million, while a similar amount went toward completion of the protracted purchase of Kenya’s chancery in London, a transaction the department says was closed in September 2025.

The project in New York involves demolishing the ambassador’s residence and redeveloping the site to include staff houses at a budgeted cost of Sh2.5 billion.

Despite the Sh550 million spent by June 2026, New York’s project was 22 percent complete, with another Sh1.95 billion required to finish it.

The department said it was still undertaking ‘the process of engaging a consultant to advise on zoning regulations, designs as per the required zoning and to seek approval’ for the project in the home to the United Nations headquarters.

The project, which commenced in July 2025, is expected to be completed in December 2028, making it one of the largest commitments in Kenya’s overseas property investment programme.

The purchase of Chancery in London, by contrast, has been fully completed after cumulative expenditure reached Sh2.67 billion, making it the most expensive completed property project in the department’s portfolio.

Across Africa, the Foreign Affairs department spent Sh440 million on property projects in Lusaka, Addis Ababa and Kinshasa, reflecting the scale of investment in Kenya’s regional diplomatic infrastructure.

The mission in Lusaka received Sh170 million, the highest allocation among the three missions in the review year, for refurbishing government properties and ongoing redevelopment of two buildings into 12 new staff houses.

The department reported that refurbishment of one staff house and construction of a water tower at the Kenya embassy’s office in Zambia had been completed. Addis Ababa received Sh150 million for repairs to the chancery and ambassador’s residence, alongside installation of CCTV and improvements to the gatehouse.

The department said the first phase, comprising ‘repair works at the Chancery, Ambassador’s Residence, and installation of CCTV and repair of gatehouse is ongoing.

The project was 42.8 percent complete by June 2026, with Sh214.2 million spent cumulatively against an estimated total cost of Sh500 million.

An additional Sh120 million was spent on properties in Kinshasa, bringing cumulative expenditure to Sh147.1 million against a project budget of Sh600 million.

The department attributed the additional expenditure partly to damage suffered by the mission during political unrest in the Democratic Republic of Congo in January 2025.

‘The mission was attacked during the recent political riots in the host country where the Chancery was vandalised,’ the department said.

It added that ‘rehabilitation of the Chancery estimated at Sh120.0 million is ongoing’, highlighting the additional financial burden arising from violent damage to Kenya’s assets in DRC, alongside those of Uganda, Rwanda, South Africa and the United States.

Other projects where Nairobi sunk millions despite limited progress include renovation of government properties in Paris, where 16.7 percent of the work had been completed.

Nairobi had spent Sh50 million on repairs to the embassy’s roof in Paris by June 2026 against a total project cost of Sh300 million, leaving Sh250 million outstanding.

The Foreign Affairs department said the work involved ‘repair of cracks and leaking roof at the Chancery’, which remained ongoing despite the project’s June 2026 expected completion date.

In Mogadishu, the government had spent Sh56.7 million against a Sh134 million budget, with completion standing at 42.3 percent.

The first phase, involving external refurbishment of government properties, construction of two security watchtowers and improvement of the grounds, had been completed.

However, the department said, ‘the construction of one watchtower, security barrier and perimeter wall repair is ongoing’.

The project illustrates the security-related costs of maintaining diplomatic infrastructure in some of Kenya’s overseas missions.

In Stockholm (Sweden), cumulative spending had reached Sh20 million in June against a Sh70 million budget, with completion at 28.6 percent.

The department said renovation of ‘the leaking roof and internal and external painting at the Ambassador’s Residence’ in Sweden’s capital was ongoing.

In Beijing, where the Sh50 million renovation project had reached 30 percent completion in June 2026, the department reported that works involving ‘plumbing, roof and painting at the Chancery and Official Residence are ongoing’.

The expenditure points to substantial financial commitments facing the government, with outstanding balances across the listed projects reaching Sh3.84 billion by June 2026.

The largest unpaid commitment relates to New York at Sh1.95 billion, followed by Lusaka at Sh397.9 million, Addis Ababa at Sh285.8 million and Paris at Sh250 million.

These balances represent future funding requirements for projects that have already absorbed billions of shillings, potentially competing with other government spending priorities.

But as the government pushes ahead with acquisitions and refurbishments, Parliament and its advisory bodies have previously questioned whether Kenya’s expansive diplomatic footprint is delivering value for money.

The Parliament Budget Office (PBO) has in the past urged policymakers to consider alternative models of expanding the country’s global diplomatic reach at a lower cost, including using honorary consuls instead of establishing fully fledged missions.

‘Honorary Consuls offer an efficient diplomatic channel for increasing a country’s diplomatic network as they are more cost-effective than fully-fledged missions because of the lower costs attached to maintaining Honorary Consuls as they serve for free and only require to be reimbursed expenses incurred in offering their services,’ the PBO wrote in a November 2021 report.

The parliamentary advisory unit on fiscal matters also recommended hiring consulates and liaison officers in countries where Kenya does not have a full embassy, arguing that such arrangements could significantly reduce the overhead costs of maintaining an extensive diplomatic network.

Concerns over the returns from overseas missions have also emerged in Parliament, particularly regarding trade and commercial offices operating within Kenyan diplomatic establishments.

The National Assembly’s Departmental Committee on Trade, Industrialisation and Cooperatives has previously questioned whether the offices were generating sufficient economic returns to justify the public money spent sustaining them abroad.

‘The committee noted that the offices of trade missions are not achieving value for money spent on sustaining them abroad. In addition, a huge share of the budgetary allocation is spent on allowances of the trade attaches,’ the committee wrote in a 2024 report.

It warned that the offices were ‘consuming resources without generating measurable returns such as getting new markets for Kenyan exports’.

The concerns introduce a wider question about the financial returns from Kenya’s overseas diplomatic presence as the government commits billions of shillings to purchasing, renovating and maintaining properties abroad.

The department’s figures show that some investments have delivered completed assets, including the London chancery purchase and renovations in Washington DC, while others remain at relatively early stages.

In Washington, the government had spent the full Sh1 billion budget by June 2026, although some refurbishment works were still ongoing.

The department said renovation of two staff houses had been completed in the 2023/24 financial year, while ‘renovation of the leaking roof at the Chancery and refurbishment of the house for the Deputy Head of Mission’ remained ongoing in Washington DC, the seat of the US government.