Editorial

he repeated delays at the Rooppur Nuclear Power Plant are understandably testing public patience.

as Bangladesh’s largest and most technologically complex development project, Rooppur carries enormous symbolic and practical weight.

every postponed milestone fuels skepticism about cost overruns, debt burdens, and execution capacity. Yet focusing only on delays risks missing the larger picture. Nuclear power is a leap into a domain where safety, regulation, and precision override speed. Fuel loading is not a ceremonial step that can be rushed to meet a calendar date; it is a point of no return.

the insistence on completing every test, certification, and international verification before loading fuel reflects caution, not failure.

in nuclear energy, delay is often the price of responsibility. Rooppur’s journey has unfolded amid extraordinary disruptions: a global pandemic, war-driven sanctions, financial transaction barriers, and domestic political upheaval. Few megaprojects anywhere in the world would have stayed on schedule under such pressures.

that construction is largely complete, safety systems installed, and Bangladeshi engineers are ready to operate the plant is a notable achievement.

the real test now lies ahead. Bangladesh must ensure transparent governance, finalize the power purchase agreement, manage long-term fuel and waste arrangements, and integrate nuclear power into a grid already under financial strain. Rooppur will only succeed if it strengthens, not complicates, the energy transition.

if handled wisely, Rooppur can anchor Bangladesh’s future with reliable, low-carbon baseload power for decades. But nuclear ambition demands nuclear discipline.

the final stretch must be guided by prudence, not pressure.

IDCOL, BTA Plan to Set Solar Power Plants in Tea Estates

A recent meeting between Infrastructure Development Company Limited (IDCOL) and the Bangladesh Tea Association focused on establishing Solar Power Plants in the tea estates of Greater Sylhet and Chattogram. The discussion centered on utilizing approximately 284 acres of unused land within tea gardens for these solar installations. Chaired by Mr. Kamran T Rahman, Chairman of the Association, the meeting took place on 20 November 2025 at the Association’s office in Mohakhali DOHS, Dhaka. Key attendees included IDCOL’s Executive Director and CEO Mr.

alamgir Morshed, Head of Renewable Energy Department Mr. Md.

enamul Karim Pavel, and Mohammad Wahidur Rahman, Head of Technical Unit Renewable Energy, along with representatives from the Bangladesh Tea Association: Mr. Wahidul Haque, Mr. Ziaul Ahsan, Mr. Mustafizur Rahman, and Dr. Kazi Muzaffar Ahmed. During the discussions, IDCOL was requested to conduct site visits at the tea gardens to assess the feasibility of establishing solar power plants. Alamgir Morshed emphasized IDCOL’s strategic role, stating, ‘IDCOL will work closely with tea estates to tap the solar power potential and remains committed to accelerating Bangladesh’s transition to clean energy through financing renewable energy, energy efficiency, and infrastructure projects.’

Bangladesh Hikes 12kg LPG Cylinder Price by Tk 38 for December

The price of liquefied petroleum gas (LPG) has increased by Tk 3.17 per unit for December, reflecting a rise in costs on the international market.

as a result, the price of the most commonly used 12kg cylinder has risen by Tk 38 to Tk 1,253.

the price was Tk 1,215 in November.

the Bangladesh Energy Regulatory Commission (BERC) announced the new LPG rates recently.

the price per kg of LPG in December will be Tk 104.41, up from Tk 101.24 the previous month.

according to BERC, the average price of propane and butane, as declared by Saudi Arabia’s state-owned company Aramco for December, is $488.50 per tonne, compared with $465.25 per tonne in November.

according to the new rates, the price of reticulated LPG is Tk 100.66 per kg, up from Tk 97.98 in the previous month.

the price of autogas for December will be Tk 57.32 per litre, an increase from Tk 55.65 per litre in November.

MSTPP Is Powering Progress With Responsibility

Maitree Super Thermal Power Plant (MSTPP) has undergone a remarkable transformation in just a few months.

the company overcame coal shortages, financial constraints, and operational challenges to bring both units to full capacity, raising availability from about 45% to over 90% and delivering the highest monthly generation in Bangladesh.

an interview highlighted that not only strategic financial interventions and disciplined operations, but also a commitment to environmental compliance, safety, and a long-term partnership with Bangladesh, underscoring how MSTPP is now powering progress with responsibility. Bangladesh India Friendship Power Company Ltd (BIFPCL) Managing Director R. Sarangapani shared his insights with Energy and Power Editor Mollah Amzad Hossain.

in the last few months, MSTPP has made significant progress.

tell us something about this turnaround.

at the time of my joining BIFPCL in March this year, there was no coal stock, with only one unit running in the last few months. With sustained efforts from my team, especially finance, we secured additional working capital more than double the existing amount, enabling continuous coal supply for sustained generation.

as a result, both units are running to full capacity from April to May. Our availability has improved from nearly 45% to more than 90%. In the last month, we generated more than 700 MUs, the highest monthly generation by any plant supplying power to Bangladesh.

throughout the month, MSTPP consistently supported the national grid by contributing nearly 11.5% of Bangladesh’s total electricity demand. MSTPP has been delivering over 600 MUs or about 8% of Bangladesh’s total electricity demand regularly.

in short, we have been able to break the vicious cycle.

at the same time, we have greatly improved our debt obligations. We have been able to service the periodic installments to the lender, and as of now, there is no outstanding amount. What does this milestone mean for Bangladesh’s energy landscape? It’s a significant achievement for Bangladesh.

it adds a reliable, efficient, and environmentally friendly base-load capacity to the grid, which is critical for sustaining economic growth, industrialization, and rural electrification.

it also exemplifies successful Indo-Bangla cooperation in large-scale infrastructure development.

the joint venture nature of BIFPCL, between NTPC and BPDB, is unique. Has this model worked in practice? Absolutely.

the joint venture combines NTPC’s global-class engineering, safety, and project execution expertise with BPDB’s deep understanding of the local landscape.

this synergy has ensured that the project meets international benchmarks while being fully integrated with Bangladesh’s power sector needs.

it’s a model worth replicating. How do you see BIFPCL’s role in Bangladesh’s energy future? BIFPCL is not just a project developer; it is a long-term strategic energy partner for Bangladesh. We aim to ensure uninterrupted, affordable, and reliable power. Beyond MSTPP, we are evaluating options for diversification, including renewables and cleaner technologies, in alignment with Vision 2041 and Sustainable Development Goals.

the project faced criticism related to environmental concerns, especially due to its proximity to the Sundarbans. What steps has BIFPCL taken to address these concerns? Environmental compliance has been a cornerstone of this project. We’ve adopted ultra-supercritical technology, installed integrated Flue Gas Desulfurization (FGD), Electrostatic Precipitators (ESPs), and Low-NOx burners.

a 275-meter chimney ensures efficient emission dispersion.

independent audits and regular inspections confirm our compliance. We are continuously meeting all the environmental parameters, which are independently sent to the pollution board periodically. We’ve also undertaken extensive tree plantation, biodiversitypreservation, and CSR activities in nearby communities. Power plants globally are under increasing pressure to decarbonize. How does a coal-based plant like MSTPP stay relevant in this context? Developing countries like Bangladesh still need base-load capacity to support growth. MSTPP uses one of the cleanest and most efficient coal technologies available today. It serves as a transitional source of power while the country builds up its renewable infrastructure.

there are various options available for reducing carbon footprint and aligning with global energy transitions like biomass co-firing and flue gas carbon capture.

these alternatives need detailed discussions with the government. What steps has BIFPCL taken to ensure safety, especially during plant commissioning and early operations? Safety is non-negotiable at BIFPCL. We’ve implemented an integrated safety management system modeled on NTPC’s framework, conducted intensive training for all staff and contractors, and established a strong culture of incident reporting and proactive risk mitigation. From a project management perspective, what lessons have been learned from implementing a megaproject like MSTPP in a foreign country? Executing a project of this scale outside one’s home country brings unique challenges-cultural, logistical, and regulatory. Key lessons include the importance of local partnerships, strong stakeholder engagement, flexibility in execution strategy, and adaptability to changing conditions.

the pandemic, for instance, tested our resilience, but we adapted swiftly and delivered.

there have been reports about disruptions in coal supply and working capital challenges.

is the plant’s operation at risk? Coal availability at sea has never been an issue.

occasionally, siltation in the channel or delays in payments have impacted unloading. However, we’ve managed operations with careful planning, coordination with MPA, and proactive procurement.

on working capital, as already told, we were able to secure sufficient value for sustaining operations. We are also planning for an enhancement to improve the situation.

there’s talk about delays in payments to coal suppliers and EPC contractors. How is BIFPCL managing its financial obligations? We’ve regularly closed our LTRs with banks and continue to meet all debt servicing obligations to EXIM Bank of India. Local liquidity issues have created temporary stress, but we are actively pursuing working capital solutions through both government and banking channels. Financial prudence and transparency guide all our actions. Critics argue that BIFPCL has created a financial burden on the government. How do you respond? That’s a misperception. MSTPP was financed via soft loans from EXIM Bank of India under sovereign arrangements. The electricity it produces offsets more expensive generation sources, helping keep tariffs stable.

over its life cycle, the project is cost-efficient and vital for national energy security.

it’s not a burden-it’s an investment in the future.

the media has often portrayed the plant as controversial. Why do you think this narrative persists? Large projects inevitably attract scrutiny. In this case, some early concerns were amplified before full facts were available. We have consistently complied with all environmental and regulatory norms.

as people now see the plant operating safely and contributing to local development, the narrative is shifting positively.

there’s often criticism in the media regarding the salaries and perks of expatriates at BIFPCL. How do you justify this in a developing country like Bangladesh? Expatriate staff from NTPC bring decades of global project execution and OandM experience.

their contributions ensured timely commissioning and operational excellence.

their remuneration follows NTPC’s salary structure and global deputation policy, and as per the agreed bilateral framework. More importantly, they are building capacity among local engineers to ensure longterm sustainability. We are the only plant among similar-sized coal plants in Bangladesh where the desk operations are managed by local people recruited by the company under the supervision of expatriates.

it’s an investment in knowledge transfer, not an overhead. Beyond power generation, what kind of community engagement or CSR initiatives is BIFPCL undertaking in the region? We are deeply committed to the communities around us. BIFPCL has built the Maitree School, supported healthcare camps, and initiated vocational training and skill development programs.

our CSR is not just about infrastructure-it’s about creating inclusive opportunities. What has been the biggest challenge during your tenure at BIFPCL? Balancing the expectations of multiple stakeholders in a dynamic environment- while maintaining technical, financial, and environmental performance-has been both the biggest challenge and the most rewarding experience. Leading a project of this complexity across borders has been an honor. What are the plans for BIFPCL beyond MSTPP? Any renewable energy aspirations? We’re exploring renewable options such as solar hybrids, battery storage, and even carbon capture.

as Bangladesh progresses toward a sustainable energy mix, BIFPCL intends to be a contributor-building on the foundation laid by MSTPP.

one final question-what is your message to the people of Bangladesh? Thank you for your trust and support. MSTPP was built with vision, dedication, and shared purpose. BIFPCL will continue to deliver power reliably, responsibly, and sustainably. We look forward to being an inseparable and integral part of Bangladesh’s energy journey in the years to come.

690 Climate-Resilient Low-Cost Housing Units Launched in Four Cities

A total of 690 climate-resilient, low-cost housing units for urban poor communities were inaugurated recently in Chandpur, Kushtia, Noakhali and Gopalganj under the Livelihoods I m p r o v e m e n t of Urban Poor C o m m u n i t i e s Project (LIUPCP). The initiative is being implemented by the Local Government Division (LGD) with support from the UK Government and the United Nations Development Program (UNDP).

the inauguration was held virtually from the Bangladesh Secretariat, with simultaneous launch events in the four project cities, according to a UNDP press release. Md. Rezaul Maksud Jahedi, Secretary of LGD and chief guest at the event, stressed the necessity of safe and dignified housing for climate-vulnerable urban populations. He noted that Bangladesh continues to face severe climate impacts despite contributing very little to global emissions.

Govt to Declare 4 Areas in 4 Dists as ‘Special Biodiversity Conservation Area’

The planet is on track to log its second hottest year on record in 2025, tied with 2023 after a historic high in 2024, Europe’s global warming monitor said recently.

the data from the Copernicus Climate Change Service reaffirms that global temperatures are on course to exceed 1.5C above pre-industrial levels — the threshold considered safer in the 2015 Paris Agreement.

temperatures rose by 1.48C on average between January and November, or ‘currently tied with 2023 to be the second-warmest year on record’, according to the service’s monthly update. ‘The three-year average for 2023-2025 is on track to exceed 1.5C for the first time,’ Samantha Burgess, strategic lead for climate at Copernicus, said in a statement. ‘These milestones are not abstract – they reflect the accelerating pace of climate change and the only way to mitigate future rising temperatures is to rapidly reduce greenhouse gas emissions,’ Burgess said.

Petrobangla Prioritizes Onshore Bidding Round to Boost Gas Output

State-run Petrobangla has prioritized launching an onshore bidding round ahead of an offshore one to ramp up the country’s overall natural gas output from local fields. ‘We are now concentrating on inviting an international tender to carry out oil and gas exploration in onshore gas blocks, especially in hilly areas,’ a senior Petrobangla official said. Raising gas production from domestic fields has become essential amid dwindling output and rising demand across industries, power plants and other major consumers, he said. ‘We are keen to float the tender soon for the onshore gas blocks,’ he added. ‘The bid round for offshore gas blocks will come later.’ Lower investment requirements and shorter exploration periods in onshore blocks have prompted Petrobangla to priorities the onshore round first, according to market insiders.

offshore exploration requires significantly higher investment and longer lead times, they added.

Yunus Seeks Stronger Trade, Energy Ties with Azerbaijan

Chief adviser M u h a m m a d Yunus recently stressed the need for stronger trade, energy and e c o n o m i c ties between B a n g l a d e s h a n d Azerbaijan. He discussed the issues when Leyla Aliyeva and Arzu Aliyeva, daughters of Azerbaijan president Ilham Aliyev, called on him at the State Guest House Jamuna.

this marked the first visit to Bangladesh by the daughters of the Azerbaijani president. Yunus recalled his many visits to Baku and his meeting with president Aliyev during the COP29 summit late last year, said chief adviser’s deputy press secretary Abul Kalam Azad. Leyla Aliyeva, vice-president of the Heydar Aliyev Foundation and founder and head of IDEA Public Union, called for enhanced environmental cooperation, particularly in wildlife protection

Bangladesh Reinstates 11 Solar Power Plants after Tari? Cuts

Bangladesh recently reinstated approvals for 11 solar plants with a combined capacity of 918 MW after developers agreed to lower tariffs, in a move expected to save the government BDT 11.69 billion ($96.2 million) per year.

the Advisers’ Council Committee on Government Purchase said the tariff reductions will save the government BDT 11.69 billion annually in power purchase costs from these plants.

according to Power Division officials, the average tariff for the projects had been $0.11/kWh. Muhammad Fouzul Kabir Khan, adviser to the Ministry of Power, said that under the renegotiated terms, power purchase costs from the 12 power plants will decrease by about $0.03/kWh. ‘Since LNG is costly, we are focusing on generating power from solar,’ he told reporters after the meeting.

after taking office in August 2024, the current government canceled approvals for 34 power plants with a combined capacity of 5,681 MW, claiming that they had been approved through unsolicited proposals and were burdened with excessively high tariffs.

the 11 solar power plants reinstated were among those previously canceled, and the Bangladesh Power Development Board (BPDB) will purchase electricity from all of them for 20 years.

Seven of a Family Burnt in Gas Blast in Agargaon

Eight people, including seven members of a family, suffered burn injuries in an explosion caused by a suspected gas line leakage at a tin-shed house in Agargaon recently.

the blast occurred at a government quarter on Paka Market Road.

the injured were taken to the burn unit of Dhaka Medical College Hospital.

the victims are Md Abdul Jalil Mia, 50; his wife Arneeza Begum, 40; their sons Asif, 19, and Sakib, 16; Asif’s wife Monira, 17; their granddaughters Eva, 6, and Isha, 6; and neighbor Firozul Alam, 35. Dr Harunur Rashid, resident surgeon at DMCH, said Firozul suffered 21 percent burns, Jalil 12 percent, and Arneeza 10 percent.

others received burns on their hands and legs. Jalil’s son-in-law, Arfan Mia, said Arneeza went to the kitchen to cook early in the morning while others were asleep.

as she lit a match, a powerful explosion occurred, triggering a blaze and injuring all eight. Neighbors rushed in to rescue them.