Novatek Proposes $950m Offshore LNG Terminal for Bangladesh

Novatek Middle East has proposed a $950 million gravity-based structure (GBS) LNG terminal in the Bay of Bengal as an alternative to Bangladesh’s planned land-based facility at Matarbari.

The company presented the preliminary concept to Petrobangla, proposing a fi xed offshore terminal with 7.5 million tonnes per annum (MTPA) of regasifi cation capacity.

Novatek estimates the facility would cost about 21% less than a conventional 7.5MTPA land-based terminal, estimated at $1.2 billion.

The fi gures, however, have not been independently verifi ed.

The proposed GBS could be built in 30-36 months and have a design life of 60-80 years.

Possible sites include deep-sea areas near Maheshkhali and Matarbari.

The facility would send regasifi ed LNG to the national grid through a subsea pipeline.

The proposal is still at an early stage, and Novatek has not submitted a formal proposal.